927 Alabama St
San Francisco permit 202010196881 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Interior remodel of rear 3 floors. no mep work. structural work req due to removal of load bearing walls. amend to pa202008061223 for additional work.
- Filed
- Oct 19, 2020
- Issued
- Feb 19, 2021 (4 months after filing)
- Completed
- Oct 21, 2021 (8 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 19, 2020 | Oct 19, 2020 | — |
Apartment and hotel inspection Building Inspection · HIS | Oct 19, 2020 | Oct 19, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 3, 2020 | Jan 12, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 3, 2020 | Jan 27, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2020 | Nov 3, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 10, 2020 | Nov 10, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 12, 2020 | Nov 30, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 30, 2020 | Dec 7, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 8, 2020 | Dec 15, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 15, 2020 | Dec 15, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 22, 2020 | Dec 22, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 23, 2020 | Jan 4, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 12, 2021 | Jan 25, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 27, 2021 | Jan 27, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2021 | Feb 4, 2021 | — |
Fire prevention review Fire Department · SFFD | Feb 4, 2021 | Feb 11, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2021 | Feb 19, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $340,000
| Name | Role | License on permit |
|---|---|---|
| Nathan Conrad Tang And Conrad Architectural | Architect | C36505 |
| Alexander Michael Santos Altos Structural Engineering | Engineer | C-84144 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025