3846 25th St
San Francisco permit 202010217035 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev to pa# 201912200177: interior remodel and some reconfiguration with new bathroom and bedroom and media room. minor interior remodel for levels 2 & 3. new dormers
- Filed
- Oct 21, 2020
- Issued
- Mar 17, 2021 (5 months after filing)
- Completed
- Jun 28, 2022 (15 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 21, 2020 | Oct 21, 2020 | — |
Zoning review Planning · CP-ZOC | Oct 23, 2020 | Feb 23, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 30, 2020 | Oct 30, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2020 | Nov 2, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Nov 2, 2020 | Nov 2, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2020 | Dec 1, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2020 | Dec 17, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2020 | Feb 25, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 22, 2021 | Jan 22, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2021 | Jan 29, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 29, 2021 | Feb 4, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2021 | Feb 5, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2021 | Feb 8, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2021 | Feb 12, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2021 | Mar 17, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Jonathan Carroll Bradley Eag Studio | Authorized agent-others | C-38856 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2014