155 Greenwich St
San Francisco permit 202011038046 · Financial District/South Beach
1st fl: partial ground fl t.i. includes demo of non-structural partitions and building (n) non-structural partitions. mep, life safety & sprinklers under separate permits. area of work provides accessory use for 1255 battery street office (b).
- Filed
- Nov 3, 2020
- Issued
- Feb 8, 2021 (3 months after filing)
- Completed
- Oct 6, 2021 (8 months after issuance)
- Review stops
- 9 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 3, 2020 | Nov 3, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2020 | Feb 1, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2020 | Nov 20, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 20, 2020 | Dec 17, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2020 | Dec 28, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 29, 2020 | Jan 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Feb 5, 2021 | Feb 5, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2021 | Feb 8, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 8, 2021 | Feb 8, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Joseph A Remling | Architect | C34144 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026