440 Geary St
San Francisco permit 202011068430 · Tenderloin
Interior t.i. and change of use from r-1 to r-2 -to rehabilitate (e) tourist hotel use to congregate housing use. the scope consists of refreshing and replacing of finishes with limited required code upgrades. no exterior work. voluntary lateral force resisting system alteration.
- Filed
- Nov 6, 2020
- Issued
- Oct 6, 2021 (11 months after filing)
- Completed
- Aug 16, 2023 (22 months after issuance)
- Review stops
- 26 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 6, 2020 | Dec 8, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2020 | Dec 9, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 8, 2020 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2020 | Jan 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 9, 2020 | Dec 18, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2020 | Dec 11, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2020 | Sep 2, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2021 | Sep 7, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Sep 15, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 1, 2021 | Sep 2, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2021 | Sep 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2021 | Sep 17, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2021 | Sep 22, 2021 | — |
Development fee collection Building Inspection · DFCU | Sep 22, 2021 | Sep 22, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2021 | Oct 6, 2021 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 7, 2021 | Oct 14, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 15, 2021 | Nov 29, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2021 | Nov 15, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2021 | Nov 16, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 15, 2021 | Nov 29, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 15, 2021 | Nov 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 15, 2021 | Oct 18, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 15, 2021 | Dec 1, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2021 | Nov 16, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2021 | Nov 12, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2021 | Dec 2, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| Michael Alan Garavaglia Garavaglia Architecture | Architect | C14833 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025