425 Geneva Av
San Francisco permit 202011179040
The work includes electrical, overhead & structural installation of traction power feeder cables, feeder breaker & switchgear, system monitoring & control, and replacement of the (e) overhead cables and supporting pole. reconstruct an (e) overhead contact system (ocs) pole and foundation and
- Filed
- Nov 17, 2020
- Issued
- Oct 14, 2021 (11 months after filing)
- Completed
- Not completed yet
- Review stops
- 7 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 17, 2020 | Nov 17, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2020 | Dec 1, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Dec 3, 2020 | Dec 3, 2020 | — |
Fire prevention review Fire Department · SFFD | Dec 3, 2020 | Dec 3, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2020 | Dec 3, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2020 | Dec 10, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2021 | Oct 14, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $3,197,014
| Name | Role | License on permit |
|---|---|---|
| Daniel Li | Engineer | C84755 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025