332 Marietta Dr
San Francisco permit 202011309839 · West of Twin Peaks
Extension of kitchen footprint at rear of house, new windows on rear facade, interior rennovations of; kitchen, living room, bathrooms, tv room.
- Filed
- Nov 30, 2020
- Issued
- Jul 29, 2022 (20 months after filing)
- Completed
- May 19, 2026 (46 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 2, 2020 | Dec 2, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 2, 2020 | May 26, 2021 | — |
Planning neighborhood notice Planning · CP-NP | May 19, 2021 | May 26, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 3, 2021 | Dec 7, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2021 | Sep 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2021 | Oct 26, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2021 | Dec 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2021 | Dec 16, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2021 | Dec 21, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 21, 2021 | Dec 21, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 21, 2021 | Jul 29, 2022 | — |
Addendum 1: Final - foundation, steel frame, superstructure, t-24 mechanical.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 1, 2023 | Aug 1, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 1, 2023 | Aug 31, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2023 | Oct 2, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2023 | Oct 3, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2023 | Oct 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2024 | Feb 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2024 | Feb 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2024 | Feb 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2024 | Feb 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2024 | Mar 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 7, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2024 | Mar 22, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Thomas A Haddock | Architect | 37464 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2014