Scope of work
As written on the permit application.

Enclosing 3 vestibules along sacramento alley. scope includes new wall & egress doors. no change to occupancy load or egress path.

Timeline
Key dates from the city record.
Filed
Dec 3, 2020
Issued
Feb 18, 2022 (15 months after filing)
Completed
Oct 7, 2022 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
7 stops across 4 departments
Comments issued
Not recorded for this permit

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 3, 2020—

Zoning review

Planning · CP-ZOC

Feb 4, 2021—

Permit Center

Permit Center · PERMIT-CTR

Jan 27, 2021—

Building plan review

Building Inspection · BLDG

Mar 2, 2021—

Fire prevention review

Fire Department · SFFD

Mar 9, 2021—

Central Permit Bureau

Building Inspection · CPB

Feb 18, 2022—

Building plan review

Building Inspection · BLDG

Feb 18, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Complete
Estimated cost
$50,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rory James Carroll

Axis Gfa Architecture & Design

ArchitectC35881
Emily Guglielmo

Martin / Martin, Inc.

EngineerS5902
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202012030185 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record