2205 Mission St
San Francisco permit 202101042026 · Mission
Priority mayor ed 13-01. to erect a type 1b, 9-story, 62 residential unit bldg with commercial space.
- Filed
- Jan 4, 2021
- Issued
- Oct 2, 2023 (33 months after filing)
- Completed
- Not completed yet
- Review stops
- 70 stops across 7 departments
- Comments issued
- 16 times, by Building Inspection, Permit Center, Public Works, CON, Fire Department, Public Utilities
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 4, 2021 | Feb 16, 2021 | — |
Building inspector Building Inspection · BID-INSP | Jan 28, 2021 | Feb 23, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 16, 2021 | Nov 2, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 16, 2021 | Feb 16, 2021 | Administrative |
Building plan review Building Inspection · BLDG | Nov 3, 2021 | Jul 13, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 3, 2021 | Jul 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2021 | Apr 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2021 | Sep 19, 2022 | — |
Urban forestry Public Works · DPW-BUF | Nov 12, 2021 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 26, 2022 | Sep 26, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jun 13, 2023 | Jun 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 20, 2023 | Sep 19, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jun 20, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 20, 2023 | Jul 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2023 | Jun 20, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 20, 2023 | Jun 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2023 | Jul 13, 2023 | — |
Zoning review Planning · CP-ZOC | Sep 19, 2023 | Sep 19, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Sep 20, 2023 | Sep 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2023 | Oct 2, 2023 | Administrative |
Building inspector Building Inspection · BID-INSP | Sep 26, 2023 | Sep 26, 2023 | Approved |
Addendum 2: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 4, 2023 | Oct 4, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Nov 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2023 | Oct 6, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Oct 4, 2023 | Feb 26, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 12, 2023 | Oct 20, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 23, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 1, 2024 | Feb 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2024 | Feb 7, 2024 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Feb 23, 2024 | Feb 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2024 | In progress | — |
Addendum 3: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2024 | Feb 12, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 9, 2024 | Feb 9, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 12, 2024 | Feb 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | — | In progress | — |
Permit Center Permit Center · PERMIT-CTR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 4: Shoring/grading
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 6, 2023 | Dec 6, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 6, 2023 | Dec 26, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2023 | Jan 10, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 6, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 5: Architectural/landscape
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 6, 2023 | Nov 8, 2023 | Administrative |
CON CON-BOND | Nov 8, 2023 | Nov 21, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Jan 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2023 | Nov 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Mar 8, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2023 | Dec 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2023 | Nov 13, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 8, 2023 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 8, 2023 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Nov 13, 2023 | Nov 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 1, 2024 | Apr 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2024 | Sep 3, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2024 | Sep 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2024 | Sep 9, 2024 | Approved |
CON CON-BOND | — | In progress | — |
Address verification Building Inspection · ADDR | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $28,000,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Jay Gelfand Gelfand Partners Architects | Architect | C17265 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Engineer | C56739 |
| Jacqueline Lingwei Luk Luk And Associates | Engineer | C75724 |
| Raymond Nim | Engineer | C90343 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026