240 Van Ness Av
San Francisco permit 202101042034 · Tenderloin
To erect a type 1-b, 8-story, 112 units, mixed-use building with ground flr office/commercial space and no basement level. 100% affordable housing.
- Filed
- Jan 4, 2021
- Issued
- Jan 24, 2022 (13 months after filing)
- Completed
- Oct 31, 2025 (45 months after issuance)
- Review stops
- 115 stops across 8 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department
- Put on hold
- 27 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 4, 2021 | Jan 8, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 8, 2021 | Apr 5, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 8, 2021 | Jan 12, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Apr 7, 2021 | Sep 1, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2021 | Oct 13, 2021 | — |
Fire prevention review Fire Department · SFFD | Apr 7, 2021 | Oct 15, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2021 | Nov 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2021 | Sep 9, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 20, 2021 | Nov 3, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 17, 2021 | Oct 15, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Oct 7, 2021 | Oct 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2021 | Oct 8, 2021 | — |
Development fee collection Building Inspection · DFCU | Nov 5, 2021 | Nov 5, 2021 | — |
Public health review Public Health · HEALTH | Nov 19, 2021 | Nov 24, 2021 | — |
Public health review Public Health · HEALTH | Nov 29, 2021 | Jan 10, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2022 | Jan 24, 2022 | — |
Addendum 1: Ground improvement
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 12, 2022 | Apr 12, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2022 | Jul 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2022 | Jul 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 12, 2022 | Dec 5, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 3, 2022 | Oct 3, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2022 | Nov 16, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2022 | Feb 9, 2023 | — |
Addendum 2: Foundation, concrete superstructure and underground utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 22, 2022 | Mar 22, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 22, 2022 | Oct 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2022 | Oct 5, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 22, 2022 | Dec 8, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 5, 2022 | Dec 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 8, 2022 | Feb 9, 2023 | — |
Addendum 3: Architectural, landscape and civil
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 12, 2022 | Jul 12, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 12, 2022 | Mar 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 12, 2022 | Aug 4, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2022 | Aug 10, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jul 12, 2022 | Mar 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2022 | Jul 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2022 | Jul 14, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2022 | Nov 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 12, 2022 | Sep 5, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Jul 28, 2022 | Jun 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 31, 2023 | Apr 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 28, 2023 | Jul 17, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 15, 2023 | Aug 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2023 | Aug 29, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2023 | Aug 17, 2023 | Approved |
Disability access review Mayor's Office on Disability · MOD | Aug 15, 2023 | Sep 5, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 15, 2023 | Aug 15, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2023 | Sep 11, 2023 | Administrative |
Addendum 4: Mechanical, electrical and plumbing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2023 | Feb 17, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 17, 2023 | Mar 13, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2023 | Sep 5, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 17, 2023 | Aug 16, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 17, 2023 | Nov 22, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 5, 2023 | Aug 17, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 16, 2023 | Aug 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2023 | Oct 4, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 4, 2023 | Oct 4, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Oct 24, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 3, 2023 | Nov 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2023 | Nov 16, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2023 | Nov 21, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 20, 2023 | Nov 21, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2023 | Nov 21, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2023 | Nov 28, 2023 | Administrative |
Addendum 5: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2023 | May 15, 2023 | — |
Building plan review Building Inspection · BLDG | May 15, 2023 | Jun 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | May 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2023 | Jun 28, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2023 | Jun 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jul 3, 2023 | — |
Addendum 6: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 17, 2023 | Jul 17, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 17, 2023 | Aug 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 17, 2023 | Aug 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 17, 2023 | Nov 2, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 7, 2023 | Nov 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 1, 2023 | Nov 1, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2023 | Dec 6, 2023 | Administrative |
Addendum 7: Fire protection - sprinkler system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 5, 2023 | Dec 5, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 5, 2023 | Dec 28, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 5, 2023 | Apr 9, 2024 | In Progress |
Fire prevention review Fire Department · SFFD | Apr 3, 2024 | Apr 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 5, 2024 | Apr 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2024 | Apr 10, 2024 | Administrative |
Addendum 8: Fire alarm system and elevator landing and horizontal exit 2-way emergency communication system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 22, 2024 | Jan 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jan 26, 2024 | Jan 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2024 | Jan 29, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 29, 2024 | May 7, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 30, 2024 | Mar 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 6, 2024 | May 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 7, 2024 | May 8, 2024 | Administrative |
Addendum 9: Solar photovoltaic system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2024 | Apr 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 18, 2024 | Apr 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 22, 2024 | Apr 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 24, 2024 | Apr 24, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 26, 2024 | Apr 30, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 30, 2024 | May 9, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2024 | May 7, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 30, 2024 | May 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 30, 2024 | Jul 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 15, 2024 | Jul 24, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 15, 2024 | Jul 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 15, 2024 | Jul 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | Jul 26, 2024 | Administrative |
Addendum 10: Dept. of public health: maher/article 22a
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 19, 2022 | Aug 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 19, 2022 | Aug 23, 2022 | — |
Public health review Public Health · HEALTH | Aug 22, 2022 | Aug 22, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2022 | Feb 9, 2023 | — |
Addendum 11: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2024 | Apr 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 22, 2024 | Apr 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2024 | Apr 22, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 22, 2024 | May 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 22, 2024 | Jul 8, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 26, 2024 | Jun 26, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2024 | Jul 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $40,100,100
| Name | Role | License on permit |
|---|---|---|
| Bruce Christian Prescott Santos Prescott And Assoc | Architect | C23687 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026