San Francisco permit 202101042034 · Tenderloin

New buildingFull plan reviewComplete
Street view · Sep 2026
Google Street View of 240 Van Ness Av, Sep 2026
Scope of work
As written on the permit application.

To erect a type 1-b, 8-story, 112 units, mixed-use building with ground flr office/commercial space and no basement level. 100% affordable housing.

Timeline
Key dates from the city record.
Filed
Jan 4, 2021
Issued
Jan 24, 2022 (13 months after filing)
Completed
Oct 31, 2025 (45 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
115 stops across 8 departments
Comments issued
13 times, by Building Inspection, Fire Department
Put on hold
27 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 8, 2021—

Zoning review

Planning · CP-ZOC

Apr 5, 2021—

Permit Processing Center

Building Inspection · PPC

Jan 12, 2022—

Disability access review

Mayor's Office on Disability · MOD

Sep 1, 2021—

Building plan review

Building Inspection · BLDG

Oct 13, 2021—

Fire prevention review

Fire Department · SFFD

Oct 15, 2021—

Street use and mapping

Public Works · DPW-BSM

Nov 22, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 9, 2021—

Zoning review

Planning · CP-ZOC

Nov 3, 2021—

Fire prevention review

Fire Department · SFFD

Oct 15, 2021—

Disability access review

Mayor's Office on Disability · MOD

Oct 21, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 8, 2021—

Development fee collection

Building Inspection · DFCU

Nov 5, 2021—

Public health review

Public Health · HEALTH

Nov 24, 2021—

Public health review

Public Health · HEALTH

Jan 10, 2022—

Central Permit Bureau

Building Inspection · CPB

Jan 24, 2022—

Addendum 1: Ground improvement

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 12, 2022—

Building plan review

Building Inspection · BLDG

Jul 22, 2022—

Street use and mapping

Public Works · DPW-BSM

Jul 21, 2022—

Permit Processing Center

Building Inspection · PPC

Dec 5, 2022—

Building plan review

Building Inspection · BLDG

Oct 3, 2022—

Street use and mapping

Public Works · DPW-BSM

Nov 16, 2022—

Central Permit Bureau

Building Inspection · CPB

Feb 9, 2023—

Addendum 2: Foundation, concrete superstructure and underground utilities

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 22, 2022—

Building plan review

Building Inspection · BLDG

Oct 17, 2022—

Street use and mapping

Public Works · DPW-BSM

Oct 5, 2022—

Permit Processing Center

Building Inspection · PPC

Dec 8, 2022—

Building plan review

Building Inspection · BLDG

Dec 6, 2022—

Central Permit Bureau

Building Inspection · CPB

Feb 9, 2023—

Addendum 3: Architectural, landscape and civil

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 12, 2022—

Building plan review

Building Inspection · BLDG

Mar 6, 2023—

Building plan review

Building Inspection · BLDG

Aug 4, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 10, 2023Approved

Fire prevention review

Fire Department · SFFD

Mar 31, 2023—

Street use and mapping

Public Works · DPW-BSM

Jul 26, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 14, 2022—

Zoning review

Planning · CP-ZOC

Nov 16, 2022—

Permit Processing Center

Building Inspection · PPC

Sep 5, 2023—

Disability access review

Mayor's Office on Disability · MOD

Jun 6, 2023—

Fire prevention review

Fire Department · SFFD

Apr 28, 2023—

Fire prevention review

Fire Department · SFFD

Jul 17, 2023—

Fire prevention review

Fire Department · SFFD

Aug 31, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Aug 29, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Aug 17, 2023Approved

Disability access review

Mayor's Office on Disability · MOD

Sep 5, 2023Approved

Zoning review

Planning · CP-ZOC

Aug 15, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Sep 11, 2023Administrative

Addendum 4: Mechanical, electrical and plumbing

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 17, 2023—

Building plan review

Building Inspection · BLDG

Mar 13, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 5, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Aug 16, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Nov 22, 2023Administrative

Fire prevention review

Fire Department · SFFD

Aug 17, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Aug 16, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 4, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Oct 4, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 24, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Nov 3, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Nov 3, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 16, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 21, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Nov 21, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 21, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Nov 28, 2023Administrative

Addendum 5: Tower crane

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 15, 2023—

Building plan review

Building Inspection · BLDG

Jun 7, 2023—

Street use and mapping

Public Works · DPW-BSM

May 24, 2023—

Permit Processing Center

Building Inspection · PPC

Jun 28, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 22, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 27, 2023—

Central Permit Bureau

Building Inspection · CPB

Jul 3, 2023—

Addendum 6: Metal stairs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 17, 2023—

Building plan review

Building Inspection · BLDG

Aug 14, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 7, 2023—

Permit Processing Center

Building Inspection · PPC

Nov 2, 2023Administrative

Fire prevention review

Fire Department · SFFD

Nov 1, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 1, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Dec 6, 2023Administrative

Addendum 7: Fire protection - sprinkler system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 5, 2023Administrative

Fire prevention review

Fire Department · SFFD

Dec 28, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Apr 9, 2024In Progress

Fire prevention review

Fire Department · SFFD

Apr 3, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 9, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 10, 2024Administrative

Addendum 8: Fire alarm system and elevator landing and horizontal exit 2-way emergency communication system

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 29, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Jan 26, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 29, 2024Administrative

Permit Processing Center

Building Inspection · PPC

May 7, 2024Administrative

Fire prevention review

Fire Department · SFFD

Mar 15, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

May 6, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 8, 2024Administrative

Addendum 9: Solar photovoltaic system

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 24, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 18, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 22, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 24, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Apr 30, 2024Administrative

Building plan review

Building Inspection · BLDG

May 9, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

May 7, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

May 3, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 25, 2024Administrative

Building plan review

Building Inspection · BLDG

Jul 24, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Jul 15, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 19, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 26, 2024Administrative

Addendum 10: Dept. of public health: maher/article 22a

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 19, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 23, 2022—

Public health review

Public Health · HEALTH

Aug 22, 2022—

Central Permit Bureau

Building Inspection · CPB

Feb 9, 2023—

Addendum 11: Errcs

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 22, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 22, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 22, 2024Administrative

Fire prevention review

Fire Department · SFFD

May 1, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 8, 2024Administrative

Fire prevention review

Fire Department · SFFD

Jun 26, 2024Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Jul 8, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Complete
Estimated cost
$40,100,100
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bruce Christian Prescott

Santos Prescott And Assoc

ArchitectC23687
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202101042034 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record