72 Rossi Av
San Francisco permit 202101112397 · Lone Mountain/USF
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa #2020-0822-2379: updated plans per puc comments & fixture counts. replace existing furnace.
- Filed
- Jan 11, 2021
- Issued
- Mar 3, 2021 (2 months after filing)
- Completed
- Jan 26, 2022 (11 months after issuance)
- Review stops
- 6 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 11, 2021 | Jan 11, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2021 | Jan 26, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2021 | Feb 8, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 9, 2021 | Feb 18, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2021 | Feb 26, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 2, 2021 | Mar 3, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $5,000
| Name | Role | License on permit |
|---|---|---|
| Neal J Z Schwartz Schwartz & Architecture | Architect | C27065 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025