710 Broderick St
San Francisco permit 202101122528 · Western Addition
Remodel kitchen, dining, and baths. add w/c. replace 5 windows and add 1 window at rear.
- Filed
- Jan 12, 2021
- Issued
- Jul 24, 2023 (30 months after filing)
- Completed
- Aug 1, 2025 (24 months after issuance)
- Review stops
- 30 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 16, 2021 | Jan 19, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 19, 2021 | May 24, 2021 | — |
Zoning review Planning · CP-ZOC | May 24, 2021 | Jul 28, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Aug 11, 2021 | Sep 22, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Oct 14, 2021 | Oct 14, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 22, 2022 | Jul 22, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2022 | Jun 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2022 | Oct 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2022 | Oct 24, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 27, 2023 | Jul 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 27, 2023 | Jun 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2023 | Jul 11, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2023 | Jul 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 14, 2023 | Jul 14, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2023 | Jul 24, 2023 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 31, 2023 | Jul 31, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jul 31, 2023 | Aug 23, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2023 | Sep 14, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2023 | Sep 15, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2023 | Sep 19, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2023 | Oct 4, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2023 | Oct 30, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2023 | Oct 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2023 | Nov 3, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2023 | Nov 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Nov 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2023 | Nov 15, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 17, 2023 | Nov 17, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2023 | Mar 22, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey S Gainer Actual-Size Architecture | Architect | C27762 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025