2011 Filbert St
San Francisco permit 202101202957 · Marina
To erect 4 stories, no basement, type v-b, 2-unit residence
- Filed
- Jan 20, 2021
- Issued
- May 15, 2024 (40 months after filing)
- Completed
- Sep 18, 2026 (28 months after issuance)
- Review stops
- 75 stops across 6 departments
- Comments issued
- 13 times, by Public Utilities, Permit Center, Building Inspection, Fire Department
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 14, 2021 | Feb 3, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 3, 2021 | Oct 10, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Feb 4, 2021 | Mar 6, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 8, 2021 | Apr 8, 2021 | Approved |
Planning neighborhood notice Planning · CP-NP | Aug 10, 2022 | Aug 23, 2022 | — |
Planning discretionary review Planning · CP-DR | Oct 3, 2022 | Mar 6, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2023 | Jun 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2023 | Jun 29, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 29, 2023 | Jul 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 3, 2023 | Jul 5, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jul 5, 2023 | Jul 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2023 | Aug 15, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 25, 2023 | Jul 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2023 | Sep 20, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Sep 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2023 | Sep 28, 2023 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Sep 29, 2023 | Oct 5, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Oct 6, 2023 | Oct 6, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2023 | May 15, 2024 | Administrative |
Addendum 1: Foundation/superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 15, 2024 | Aug 27, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 26, 2024 | Aug 26, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 26, 2024 | Oct 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 7, 2024 | Oct 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2024 | Oct 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 10, 2024 | Nov 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 10, 2024 | Oct 16, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 10, 2024 | Sep 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 25, 2024 | Nov 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Aug 6, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 27, 2025 | Aug 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2025 | Sep 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 27, 2025 | Aug 29, 2025 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2025 | Sep 18, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Sep 5, 2025 | Sep 11, 2025 | Approved |
Addendum 2: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 16, 2025 | Sep 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2025 | Sep 4, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2025 | Sep 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2025 | Sep 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2025 | Sep 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 4, 2025 | Sep 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2025 | Sep 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 4, 2025 | Sep 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2025 | Sep 8, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 4, 2025 | Oct 1, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 4, 2025 | Feb 3, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 18, 2025 | Sep 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2025 | Sep 19, 2025 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Sep 19, 2025 | Sep 19, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 1, 2025 | Oct 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 27, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 27, 2025 | Nov 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 27, 2025 | Nov 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 27, 2025 | Nov 7, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 27, 2025 | Oct 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 27, 2025 | Nov 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2025 | Oct 28, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 27, 2025 | Nov 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 12, 2025 | Jan 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2025 | Dec 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 12, 2025 | Dec 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2025 | Dec 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 12, 2025 | Dec 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2025 | Dec 19, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 12, 2025 | Dec 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 26, 2026 | Jan 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2026 | Jan 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 26, 2026 | Feb 2, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2026 | Jan 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 26, 2026 | Feb 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2026 | Jan 29, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 26, 2026 | Jan 30, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 27, 2026 | Jan 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2026 | Feb 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $1,675,000
| Name | Role | License on permit |
|---|---|---|
| Mark Jeffrey Topetcher Topetcher Architectural | Project contact | C21678 |
| Zachary Joseph Maddry Dmarc Studio | Architect | C30718 |
| Jacqueline Lingwei Luk Luk And Associates | Engineer | C75724 |
| Randy Edward Collins Ftf Engineering, Inc | Engineer | S4802 |
| David W Kane Harrell Kane S.E. Inc. | Engineer | S-5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022