323 Hearst Av
San Francisco permit 202101223153 · West of Twin Peaks
In response to nov 202034571, we are applying for a permit for the new work: expand horizontally at rear, expand vertically for new floor level to existing single-family dwelling.
- Filed
- Jan 22, 2021
- Issued
- Mar 22, 2023 (26 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Jan 22, 2021 | Jan 22, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2021 | Feb 9, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 9, 2021 | Nov 23, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Nov 24, 2021 | Jan 25, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 26, 2022 | Jan 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2023 | Jan 31, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2023 | Feb 2, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 2, 2023 | Feb 6, 2023 | — |
Development fee collection Building Inspection · DFCU | Feb 7, 2023 | Feb 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 7, 2023 | Feb 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2023 | Mar 22, 2023 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 22, 2023 | Sep 27, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 27, 2023 | Nov 29, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 30, 2023 | Jan 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2024 | Jan 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 19, 2024 | Jan 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2024 | Feb 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2024 | Feb 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 8, 2024 | Mar 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2024 | Mar 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2024 | Mar 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 27, 2024 | Mar 27, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2024 | Jul 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $321,708
| Name | Role | License on permit |
|---|---|---|
| Tom Amedeo Mcelroy Mcelroy Architecture | Architect | C30930 |
| Julia Yung-Ling Chen Julia Y. Chen Design Inc. | Engineer | S4498 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016