618 Eugenia Av
San Francisco permit 202101233203 · Bernal Heights
Alteration of (e) non-conforming basement/ interior remodel & new interior access stair, new light well.structural foundation, floor framing & wall framing to support alterations. remove & replace (e) west courtyard slab & north & south property line fences & gate.
- Filed
- Jan 23, 2021
- Issued
- May 5, 2022 (15 months after filing)
- Completed
- Apr 15, 2025 (35 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 27, 2021 | Jan 27, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2021 | Jun 17, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 5, 2021 | May 6, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Feb 15, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2021 | Dec 7, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2021 | Feb 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2021 | Dec 30, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 9, 2021 | Dec 9, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 30, 2021 | Dec 30, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 3, 2022 | Mar 23, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 15, 2022 | Feb 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2022 | Mar 17, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2022 | Mar 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 28, 2022 | Mar 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2022 | May 5, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $735,000
| Name | Role | License on permit |
|---|---|---|
| Joseph G Garcia Avelar | Architect | C26356 |
| Jeff Glen Williams Jeff Williams | Engineer | S3876 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025