570 Beale St
San Francisco permit 202101253240 · Financial District/South Beach
Bldg 4: update existing roof deck.
- Filed
- Jan 25, 2021
- Issued
- May 2, 2022 (15 months after filing)
- Completed
- Feb 9, 2023 (9 months after issuance)
- Review stops
- 13 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 25, 2021 | Mar 26, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 26, 2021 | May 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 26, 2021 | Oct 28, 2021 | — |
Building plan review Building Inspection · BLDG | May 21, 2021 | Oct 25, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2021 | Oct 8, 2021 | — |
Electrical plan review Building Inspection · MECH-E | May 21, 2021 | Aug 17, 2021 | — |
Fire prevention review Fire Department · SFFD | May 21, 2021 | Oct 21, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 24, 2021 | Aug 17, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 8, 2021 | Oct 18, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2021 | Oct 28, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2021 | Oct 18, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2021 | Oct 25, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2021 | May 2, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $45,000
| Name | Role | License on permit |
|---|---|---|
| Gerhard Walter Mayer Gglo Design | Architect | C29592 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025