139 Edinburgh St
San Francisco permit 202101253267 · Excelsior
Horizontal expansion to add breakfast area on 1st fl & bedroom & bathroom on 2nd fl. renovation of bathrooms. replace windows as noted
- Filed
- Jan 25, 2021
- Issued
- Mar 23, 2023 (26 months after filing)
- Completed
- Not completed yet
- Review stops
- 34 stops across 5 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2021 | Apr 16, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 16, 2021 | Mar 10, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jan 7, 2022 | Jan 19, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 9, 2022 | Mar 9, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 11, 2022 | Apr 26, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2022 | Jan 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2022 | Jul 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2022 | Sep 12, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2023 | Mar 6, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 6, 2023 | Mar 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 17, 2023 | Mar 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 17, 2023 | Mar 23, 2023 | — |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 23, 2024 | Mar 1, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 29, 2024 | Feb 29, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 29, 2024 | Feb 29, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 29, 2024 | Feb 29, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2024 | Mar 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 7, 2024 | Mar 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2024 | Mar 11, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 11, 2024 | Oct 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 12, 2024 | May 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2024 | Apr 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2024 | Mar 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2024 | Mar 26, 2024 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 19, 2024 | Apr 19, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2024 | Aug 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2024 | Aug 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2024 | Aug 19, 2024 | — |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Oct 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2024 | Mar 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $304,974
| Name | Role | License on permit |
|---|---|---|
| Christina Yea Toy Cyt Associates | Architect | C-30582 |
| Jennifer Sadie Tulley | Architect | C33069 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019