1100 Van Ness Av
San Francisco permit 202101263327 · Tenderloin
This project consists of adding (2) dc fast charging stations and electrical panel at garage level g2
- Filed
- Jan 26, 2021
- Issued
- Apr 6, 2021 (2 months after filing)
- Completed
- Jan 5, 2022 (9 months after issuance)
- Review stops
- 13 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 26, 2021 | Jan 26, 2021 | — |
Code enforcement Building Inspection · CES | Jan 26, 2021 | Mar 15, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 28, 2021 | Jan 28, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 12, 2021 | Feb 12, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2021 | Feb 12, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Feb 12, 2021 | Feb 12, 2021 | — |
Fire prevention review Fire Department · SFFD | Feb 17, 2021 | Feb 23, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 23, 2021 | Mar 3, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Mar 4, 2021 | Mar 4, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2021 | Mar 10, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2021 | Mar 10, 2021 | — |
Fire prevention review Fire Department · SFFD | Mar 25, 2021 | Mar 25, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2021 | Apr 6, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $13,400
| Name | Role | License on permit |
|---|---|---|
| Madelyn Mayme Mcclellan | Architect | C37097 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026