CheckMyDesigner

319 Bay Shore Bl

San Francisco permit 202101273419 · Bayview Hunters Point

New buildingFull plan reviewIssued
Street view · Jul 2022
Google Street View of 319 Bay Shore Bl, Jul 2022
Scope of work
As written on the permit application.

Construct gas station and convenience store.(n) 1,385 sf. convenience store and a new 2,856 sf. fueling canopy covering four (4) new fuel dispensers. installing two (2) new underground storage tanks. the site improvements include parking stalls, accessible path of travel to the right-of-way

Timeline
Key dates from the city record.
Filed
Jan 27, 2021
Issued
Aug 21, 2025 (55 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
17 stops across 6 departments
Comments issued
Once, by Public Health
Put on hold
6 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 2, 2021—

Zoning review

Planning · CP-ZOC

Jun 23, 2021—

Building plan review

Building Inspection · BLDG

Mar 8, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Mar 3, 2022—

Fire prevention review

Fire Department · SFFD

Mar 15, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 27, 2022—

Street use and mapping

Public Works · DPW-BSM

Nov 16, 2021—

Public health review

Public Health · HEALTH

Mar 23, 2022—

Public Health

HEALTH-HM

Mar 24, 2022—

Public Health

HEALTH-MH

Mar 28, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2024Approved

Public Health

HEALTH-MH

Mar 13, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 20, 2025Approved

Zoning review

Planning · CP-ZOC

Jul 28, 2025Approved

Permit Processing Center

Building Inspection · PPC

Aug 8, 2025Administrative

Building plan review

Building Inspection · BLDG

Aug 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 21, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$1,100,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Muthana Ismail IbrahimArchitectC-29627
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202101273419 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record