900 Hudson Av

San Francisco permit 202101273429 · Bayview Hunters Point

Retaining wall or site workFull plan reviewComplete
Scope of work
As written on the permit application.

Remove soil and backfill equivalen with clean material to depth ranging from 2 ft - 4 ft- compaction to follow. remove sediment in submerged lots and backfill with equivalent material. compaction only required for areas outside of the submerged zone.

Timeline
Key dates from the city record.
Filed
Jan 27, 2021
Issued
Jun 7, 2021 (4 months after filing)
Completed
Apr 22, 2024 (34 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
6 stops across 3 departments
Comments issued
Not recorded for this permit
Put on hold
Once

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 3, 2021—

Building plan review

Building Inspection · BLDG

May 7, 2021—

Street use and mapping

Public Works · DPW-BSM

May 28, 2021—

Public health review

Public Health · HEALTH

Mar 4, 2021—

Permit Processing Center

Building Inspection · PPC

Jun 1, 2021—

Central Permit Bureau

Building Inspection · CPB

Jun 7, 2021—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Grade or quarry or fill or excavate
Status
Complete
Estimated cost
$105,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael Patrick WhelanEngineerC69833
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202101273429 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record