900 Innes Av
San Francisco permit 202101273434 · Bayview Hunters Point
Work to occur around structure/cottage. offset work 5-ft from structure/cottage; minimal grading work and fill proposed around offset perimeter.
- Filed
- Jan 27, 2021
- Issued
- Jun 9, 2021 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 6 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 27, 2021 | Mar 3, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 3, 2021 | May 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2021 | May 28, 2021 | — |
Public health review Public Health · HEALTH | Mar 3, 2021 | May 28, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 3, 2021 | Jun 1, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 1, 2021 | Jun 9, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Grade or quarry or fill or excavate
- Status
- Expired
- Estimated cost
- $7,500
| Name | Role | License on permit |
|---|---|---|
| Michael Patrick Whelan | Engineer | C69833 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026