43 Molimo Dr
San Francisco permit 202101283525 · West of Twin Peaks
Phase ii 375 sq.ft. rear addition with two 1st floor bedrooms and 2nd floor roof deck (phase i improvements to the existing structure per approved application 2019-1218-9834 is about to be completed)
- Filed
- Jan 28, 2021
- Issued
- Dec 28, 2021 (11 months after filing)
- Completed
- Dec 26, 2023 (24 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 26, 2021 | Feb 2, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 2, 2021 | Jul 1, 2021 | — |
Planning neighborhood notice Planning · CP-NP | May 13, 2021 | May 18, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 2, 2021 | Sep 2, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2021 | Sep 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2021 | Oct 1, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 5, 2021 | Oct 5, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2021 | Dec 28, 2021 | — |
Addendum 1: Architectural, structural, t24, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 10, 2022 | May 10, 2022 | — |
Building plan review Building Inspection · BLDG | May 10, 2022 | Jul 12, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2022 | Aug 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2022 | Mar 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2022 | Aug 11, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 8, 2023 | Mar 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 8, 2023 | Mar 15, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Michael Andreas Froehlich Michael Froehlich Architect | Architect | C24111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025