2285 Jerrold Av
San Francisco permit 202101303693 · Bayview Hunters Point
Erect 6 stories commerical and self storage building
- Filed
- Jan 30, 2021
- Issued
- Sep 2, 2022 (19 months after filing)
- Completed
- Not completed yet
- Review stops
- 44 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 11 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Public health review Public Health · HEALTH | Apr 12, 2011 | Apr 12, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2021 | Feb 9, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 9, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2021 | Mar 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 15, 2021 | Oct 19, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 11, 2022 | Jan 13, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 14, 2022 | Mar 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2022 | May 3, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 5, 2022 | Apr 12, 2022 | — |
Development fee collection Building Inspection · DFCU | Apr 14, 2022 | Apr 14, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2022 | Apr 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2022 | Apr 26, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 27, 2022 | May 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 5, 2022 | May 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 6, 2022 | Sep 2, 2022 | — |
Addendum 1: Foundation - superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2022 | Nov 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 29, 2022 | Sep 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Nov 30, 2022 | May 4, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2022 | Mar 18, 2026 | — |
Building plan review Building Inspection · BLDG | May 4, 2023 | May 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2026 | Mar 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2026 | Apr 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 17, 2026 | Aug 18, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 31, 2026 | Aug 31, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2026 | Sep 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2026 | In progress | In Progress |
Development fee collection Building Inspection · DFCU | Sep 30, 2026 | Sep 30, 2026 | Administrative |
Addendum 2: Architectural/civil/electrical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2023 | Mar 7, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2023 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2023 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Mar 7, 2023 | In progress | — |
Fire prevention review Fire Department · SFFD | Mar 7, 2023 | Mar 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2023 | In progress | — |
Urban forestry Public Works · DPW-BUF | Mar 7, 2023 | Jul 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2023 | Mar 24, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 7, 2023 | Mar 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2023 | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 9, 2022 | Oct 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 24, 2022 | Oct 31, 2022 | — |
Public health review Public Health · HEALTH | Oct 25, 2022 | Oct 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2022 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $36,000,000
| Name | Role | License on permit |
|---|---|---|
| Anthony A Pantaleoni Kotas/Pantaleoni Architects | Architect | C14072 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Engineer | C56739 |
| Eugene Yu-Ming Tuan Tuan & Robinson Str. Engineer | Engineer | S3982 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026