649 28th St
San Francisco permit 202102013766 · Noe Valley
Addition to rear of 1st and 2nd floors and addition of new 3rd floor. expand existing 2,105 gsf 2-bedroom, 1 bath house to a 4,227 gsf-5 bedroom 3.5-bath house.
- Filed
- Feb 1, 2021
- Issued
- Aug 29, 2022 (19 months after filing)
- Completed
- Not completed yet
- Review stops
- 32 stops across 6 departments
- Comments issued
- None
- Put on hold
- 9 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 1, 2021 | Feb 11, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 12, 2021 | Mar 16, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Oct 8, 2021 | Nov 24, 2021 | — |
Planning discretionary review Planning · CP-DR | Nov 24, 2021 | Mar 4, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 10, 2022 | Mar 10, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 21, 2022 | May 4, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 4, 2022 | May 6, 2022 | — |
Urban forestry Public Works · DPW-BUF | May 17, 2022 | Jun 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 18, 2022 | Jun 8, 2022 | — |
Zoning review Planning · CP-ZOC | May 24, 2022 | Jun 3, 2022 | — |
Development fee collection Building Inspection · DFCU | Jun 28, 2022 | Jun 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 29, 2022 | Jul 6, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 8, 2022 | Jul 11, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 12, 2022 | Jul 12, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 12, 2022 | Aug 29, 2022 | — |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2023 | Feb 1, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2023 | Jun 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2023 | Jun 23, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2023 | Oct 24, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 1, 2023 | Mar 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2023 | Feb 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 1, 2023 | Oct 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jun 23, 2023 | Jul 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2023 | Jul 7, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 23, 2023 | Aug 7, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2023 | Jun 30, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 11, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2023 | Jul 11, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2023 | Jul 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2023 | Jul 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Oct 24, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 25, 2023 | Dec 2, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Jonathan N Pearlman Elevation Architects | Architect | C26034 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022