508 Belvedere St
San Francisco permit 202102044034 · Haight Ashbury
Horizontal expansion in the rear on first and second floors. demo of rear facade, relocate a kitchen, relocate two bathrooms, rearrange solar panels.
- Filed
- Feb 4, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 15 stops across 5 departments
- Comments issued
- None
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 4, 2021 | Feb 17, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2021 | Oct 15, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Aug 11, 2021 | Aug 11, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2021 | Jan 11, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2022 | Mar 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 19, 2022 | Jan 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2022 | Feb 24, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2022 | Mar 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2022 | Mar 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2022 | Mar 10, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 10, 2022 | Mar 10, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2022 | Mar 28, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 11, 2022 | Mar 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2022 | In progress | In Progress |
Mechanical and energy plan review Building Inspection · MECH | — | Mar 10, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Anne Noelle Fougeron | Engineer | C18901 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022