335 A Hill St
San Francisco permit 202102054125 · Noe Valley
Erect new 1 story type-v, 1-unit residence (sfd) at rear of lot.
- Filed
- Feb 5, 2021
- Issued
- Dec 29, 2022 (23 months after filing)
- Completed
- May 7, 2024 (16 months after issuance)
- Review stops
- 17 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 5, 2021 | Feb 17, 2021 | — |
Building inspector Building Inspection · BID-INSP | Feb 9, 2021 | Feb 9, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 10, 2021 | Aug 31, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 17, 2021 | Nov 10, 2022 | — |
Planning neighborhood notice Planning · CP-NP | May 4, 2021 | Jun 3, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Feb 16, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Feb 24, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Sep 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2021 | Aug 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 12, 2021 | Dec 13, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2021 | Dec 17, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2021 | Jan 24, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 17, 2022 | Aug 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2022 | Sep 27, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2022 | Sep 29, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 30, 2022 | Nov 8, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 10, 2022 | Dec 29, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Adriana Daringa Adbc Architecture | Architect | C33174 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025