214 Duncan St #0
San Francisco permit 202102054162 · Noe Valley
Remodel 3rd fl single family condo including addition of 47 sq ft of conditioned space (n) bath within (e) roof envelope & addition of (n) 3-story deck @ rear of bldg. (e) kitchen & bath are being remodeled including associated plumbing & electrical work
- Filed
- Feb 5, 2021
- Issued
- Nov 22, 2021 (10 months after filing)
- Completed
- Apr 13, 2023 (17 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 23, 2021 | Feb 25, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 26, 2021 | Sep 14, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Jul 26, 2021 | Sep 14, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2021 | Oct 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2021 | Oct 28, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2021 | Nov 12, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 17, 2021 | Nov 17, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2021 | Nov 22, 2021 | — |
Addendum 1: Architectural,structural,foundation,t24,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 10, 2021 | Dec 10, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 10, 2021 | Feb 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2022 | Mar 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2022 | Mar 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2022 | Mar 30, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 30, 2022 | Apr 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2022 | Apr 6, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Michael J Baushke Apparatus Architecture | Architect | C25953 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026