555 Bryant St
San Francisco permit 202102124635 · South of Market
To erect a mixed use residential with 500 dwelling units,type 1 with 125 accessory parking spaces, 16 stories and 3 basement y
- Filed
- Feb 12, 2021
- Issued
- Nov 22, 2022 (21 months after filing)
- Completed
- Not completed yet
- Review stops
- 155 stops across 8 departments
- Comments issued
- 27 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 15 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 12, 2021 | Feb 24, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 24, 2021 | Nov 18, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 4, 2021 | Aug 5, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2021 | Oct 14, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 21, 2021 | Oct 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2021 | Aug 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2021 | Aug 26, 2022 | — |
CON CON-BOND | Jul 12, 2022 | Sep 13, 2022 | — |
Public health review Public Health · HEALTH | Jul 22, 2022 | Jul 22, 2022 | — |
Public Health HEALTH-MH | Jul 22, 2022 | Jul 22, 2022 | — |
Public Health HEALTH-HM | Jul 22, 2022 | Jul 22, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 26, 2022 | Oct 17, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2022 | Oct 17, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 18, 2022 | Oct 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2022 | Oct 19, 2022 | — |
Urban forestry Public Works · DPW-BUF | Oct 18, 2022 | Oct 20, 2022 | — |
Public Health HEALTH-HM | Oct 18, 2022 | Oct 18, 2022 | — |
Development fee collection Building Inspection · DFCU | Oct 19, 2022 | Oct 19, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2022 | Nov 17, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2022 | Nov 22, 2022 | — |
Addendum 1: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 23, 2022 | Nov 23, 2022 | — |
Public health review Public Health · HEALTH | Nov 23, 2022 | Dec 13, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 23, 2022 | Dec 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 14, 2022 | Dec 29, 2022 | — |
Addendum 2: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2022 | Nov 30, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2022 | Feb 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2022 | Dec 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 30, 2022 | Feb 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2023 | Feb 7, 2023 | — |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2022 | Nov 30, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2022 | Sep 5, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2022 | Dec 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 30, 2022 | Oct 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2023 | Sep 13, 2023 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2023 | Oct 4, 2023 | Administrative |
Addendum 4: Arch mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 24, 2023 | Jan 24, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2023 | Jun 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2023 | Jul 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 24, 2023 | Jul 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2023 | Mar 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 24, 2023 | Mar 20, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 30, 2023 | Jun 28, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2023 | Jul 11, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 28, 2023 | Jun 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 1, 2023 | Aug 1, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Sep 8, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2023 | Oct 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2023 | Sep 28, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Dec 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2023 | Nov 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 19, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Jan 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 23, 2024 | Jan 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Feb 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2024 | Feb 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 12, 2024 | Feb 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 15, 2024 | Feb 15, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2024 | Feb 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 4, 2024 | Mar 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 5, 2024 | Mar 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2024 | Mar 7, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2024 | Mar 7, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Mar 19, 2024 | Mar 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2024 | Mar 21, 2024 | Administrative |
Addendum 5: Exterior skin
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 15, 2024 | May 29, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 17, 2024 | May 17, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 21, 2024 | May 21, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 29, 2024 | May 29, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | May 31, 2024 | May 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 31, 2024 | Jun 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 31, 2024 | Jun 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 31, 2024 | Jun 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 31, 2024 | Jan 31, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 5, 2024 | Jun 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 23, 2025 | Jan 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 29, 2025 | Jan 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2025 | Jan 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2025 | Feb 3, 2025 | Administrative |
Addendum 6: Metal stair
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 31, 2023 | Jun 2, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 2, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 2, 2023 | Aug 16, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 2, 2023 | Aug 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2023 | Aug 17, 2023 | Administrative |
Addendum 7: Fire sprinkler/protection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2023 | Jun 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2023 | Apr 8, 2024 | — |
Fire prevention review Fire Department · SFFD | Jun 22, 2023 | Aug 24, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2024 | Mar 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 8, 2024 | Apr 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2024 | Apr 8, 2024 | Administrative |
Addendum 8: Fire alarm + 2 way ecs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 21, 2024 | May 23, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2024 | May 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 23, 2024 | May 23, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 23, 2024 | May 29, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 23, 2024 | Jun 24, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 21, 2024 | Jun 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2024 | Jun 24, 2024 | Administrative |
Addendum 9: Generator / fuel oil
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 12, 2023 | Oct 12, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 12, 2023 | Oct 27, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 12, 2023 | Nov 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 12, 2023 | Nov 6, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Oct 12, 2023 | Oct 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 12, 2023 | May 6, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Nov 1, 2023 | Dec 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 6, 2023 | Mar 7, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 1, 2024 | Apr 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2024 | Apr 23, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 17, 2024 | Apr 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 2, 2024 | May 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 3, 2024 | Approved |
Public health review Public Health · HEALTH | May 2, 2024 | May 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 6, 2024 | May 6, 2024 | Administrative |
Addendum 10: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 20, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 20, 2023 | Nov 7, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 20, 2023 | Dec 7, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 6, 2023 | Dec 6, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 7, 2023 | Dec 14, 2023 | Administrative |
Addendum 11: Window washing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 18, 2024 | Apr 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 22, 2024 | Apr 22, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 24, 2024 | Apr 24, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 26, 2024 | Apr 26, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | May 6, 2024 | May 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2024 | May 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2024 | May 7, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 6, 2024 | May 20, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 20, 2024 | May 21, 2024 | Administrative |
Addendum 12: Fire service access elevator
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 28, 2024 | Sep 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 4, 2024 | Sep 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2024 | Sep 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 10, 2024 | Sep 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 10, 2024 | Sep 24, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2024 | Oct 9, 2024 | Administrative |
Addendum 13: Storefront and misc exterior elements
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 20, 2025 | Jun 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2025 | Jun 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 3, 2025 | Jul 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jul 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2025 | Jul 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2025 | Jun 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 3, 2025 | Jun 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 3, 2025 | Jul 10, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2025 | Jun 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2025 | Jul 18, 2025 | Administrative |
Addendum 14: Interior code signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 29, 2025 | May 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 16, 2025 | May 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 16, 2025 | Jun 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 16, 2025 | May 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 16, 2025 | Aug 14, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 26, 2025 | Jun 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 13, 2025 | Aug 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 13, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Aug 15, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $200,000,000
| Name | Role | License on permit |
|---|---|---|
| Peter J Noone Solomon Cordwell Buenz | Architect | C31296 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026