159 10th Av
San Francisco permit 202102164755 · Inner Richmond
Addition & remodel of single family dwelling including kitchen, powder rm, family rm, master bath, laundry & half bath. (2) additions: 2nd fl infill on (e) structure. vertical ext of proposed 3rd fl addition is 15'-0" above (e) roof parapet & horizontal ext is 14'0". (2) decks proposed, rain
- Filed
- Feb 16, 2021
- Issued
- Nov 19, 2021 (9 months after filing)
- Completed
- Jan 16, 2025 (38 months after issuance)
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 16, 2021 | Feb 26, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 26, 2021 | Oct 22, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Aug 30, 2021 | Sep 2, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2021 | Oct 26, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 26, 2021 | Nov 3, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 26, 2021 | Nov 3, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2021 | Nov 3, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2021 | Nov 3, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2021 | Nov 4, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2021 | Nov 19, 2021 | — |
Addendum 1: Architectural,structural,t-24,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 7, 2021 | Dec 7, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 7, 2021 | May 13, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 7, 2021 | May 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2022 | Apr 25, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 25, 2022 | Jun 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2022 | May 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2022 | Jun 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 21, 2022 | Jun 28, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $325,000
| Name | Role | License on permit |
|---|---|---|
| John Clement Clarke John Clarke Architects | Architect | C29106 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020