838 Kearny St
San Francisco permit 202102174826 · Chinatown
Project comprises of the interior fit out of the basement floor including 1 new gymnasium, 3 new classrooms and 2 new student restrooms.
- Filed
- Feb 17, 2021
- Issued
- May 4, 2022 (14 months after filing)
- Completed
- Nov 9, 2023 (18 months after issuance)
- Review stops
- 16 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 17, 2021 | Feb 17, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 19, 2021 | Apr 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2021 | Mar 31, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Apr 1, 2021 | Apr 1, 2021 | — |
Fire prevention review Fire Department · SFFD | Apr 1, 2021 | Apr 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2021 | Apr 14, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2021 | Apr 26, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Apr 26, 2021 | Oct 14, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2022 | Mar 22, 2022 | — |
Intake Building Inspection · INTAKE | Mar 23, 2022 | Mar 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2022 | Mar 23, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 23, 2022 | Mar 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 23, 2022 | Mar 23, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 29, 2022 | Apr 29, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 29, 2022 | Apr 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 4, 2022 | May 4, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $3,000,000
| Name | Role | License on permit |
|---|---|---|
| Pauline Margaret Souza Wrbs Studio | Architect | C24532 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026