Scope of work
As written on the permit application.

Addition & remodel at main level for new kitchen, bedroom, full bath, & powder room. addition & remodel to convert to habitable space w/ 2 bedrooms, bathroom, laundry room, & closets. garage & (e) storage to remain, create new mechanical enclosure. new decks at main level in rear w/ stairs to yard.

Timeline
Key dates from the city record.
Filed
Mar 9, 2021
Issued
Jun 5, 2025 (51 months after filing)
Completed
Feb 4, 2026 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 4 departments
Comments issued
8 times, by Building Inspection, Public Works
Put on hold
Once
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 16, 2021—

Zoning review

Planning · CP-ZOC

Aug 30, 2023Approved

Permit Processing Center

Building Inspection · PPC

Jun 3, 2025Administrative

Planning neighborhood notice

Planning · CP-NP

Apr 19, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 25, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 4, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 12, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 7, 2023Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 5, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 25, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Apr 8, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 18, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 27, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 25, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 18, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 4, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jan 13, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 11, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 7, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 27, 2024Approved

Building plan review

Building Inspection · BLDG

May 1, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 7, 2025Approved

Zoning review

Planning · CP-ZOC

May 13, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 13, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 5, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$322,751
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ethan C Andersen

Drafting Cafe Architects

ArchitectC34235
Matthew Bryan Tropp

Ashley & Vance

EngineerS5683
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202103096191 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record