31 Houston St
San Francisco permit 202103116371 · Russian Hill
(e) is a residential three-story structure: third floor has 3 dwelling units, second floor has 3 dwelling units, first floor has one-car garage, storage spaces, and one dwelling unit. convert (e) 1st floor garage and storage area into (2) new adu per ord. #162-16. total of nine units.
- Filed
- Mar 11, 2021
- Issued
- Jun 7, 2023 (27 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Mar 11, 2021 | Mar 18, 2021 | — |
Code enforcement Building Inspection · CES | Mar 18, 2021 | Feb 2, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 18, 2021 | Feb 10, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 18, 2021 | Mar 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 18, 2021 | Mar 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2021 | Jan 24, 2022 | — |
Urban forestry Public Works · DPW-BUF | Mar 18, 2021 | Mar 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2021 | Mar 24, 2021 | — |
Fire prevention review Fire Department · SFFD | Mar 18, 2021 | Mar 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2022 | Mar 3, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 14, 2022 | Jul 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2022 | Mar 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2022 | Jul 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2022 | Jul 7, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 22, 2022 | Jun 2, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2023 | Feb 8, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 30, 2023 | Jan 30, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2023 | Jan 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2023 | Jan 31, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jan 30, 2023 | Mar 13, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 30, 2023 | Jan 31, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2023 | Jan 31, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 10, 2023 | Jun 6, 2023 | — |
Development fee collection Building Inspection · DFCU | Mar 13, 2023 | Mar 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Jun 7, 2023 | — |
Building Inspection 417-86 | Mar 27, 2023 | Apr 12, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Van Thai Ly Van T. Ly & Associates | Architect | C-25710 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019