630 Geary St
San Francisco permit 202103116398 · Tenderloin
Comply w/nov 202173833 & 202173835. convert(e) basement entertainment rm to(n) storage rm w/full bath, convert(e) communal baths on flrs 1-5 to (n) utility closets w/janitorial sinks, 1/f reconfig/change use of 2(e) rms to (n) ofc & restore kitchen to mgrs dwelling unit. convert 30(e) guest rm
- Filed
- Mar 11, 2021
- Issued
- Oct 7, 2022 (19 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 11, 2021 | Mar 11, 2021 | — |
Zoning review Planning · CP-ZOC | May 21, 2021 | Aug 25, 2021 | — |
Apartment and hotel inspection Building Inspection · HIS | May 28, 2021 | Aug 21, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 19, 2021 | Nov 19, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 22, 2021 | Nov 29, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2021 | Dec 23, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 23, 2021 | Dec 23, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 7, 2022 | Mar 7, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2022 | Mar 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 20, 2022 | Apr 20, 2022 | — |
Fire prevention review Fire Department · SFFD | May 17, 2022 | May 17, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jul 11, 2022 | Jul 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2022 | Jul 11, 2022 | — |
Development fee collection Building Inspection · DFCU | Jul 12, 2022 | Jul 12, 2022 | — |
Intake Building Inspection · INTAKE | Aug 29, 2022 | Aug 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2022 | Sep 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2022 | Sep 20, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 22, 2022 | Sep 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2022 | Sep 22, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 26, 2022 | Sep 26, 2022 | — |
Building inspector Building Inspection · BID-INSP | Sep 27, 2022 | Sep 27, 2022 | — |
Electrical inspector Building Inspection · EID-INSP | Sep 28, 2022 | Sep 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2022 | Oct 7, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 31, 2022 | Oct 31, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| E Andrew Faust Mw Design | Architect | C28181 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026