148 Randall St
San Francisco permit 202103156519 · Glen Park
Remodel one bath, convert master closet to bath and closet. convert part of 2nd closet for stacked washer/dryer. expand a 3rd closet. all work on 2nd floor. no exterior work.
- Filed
- Mar 15, 2021
- Issued
- May 17, 2021 (2 months after filing)
- Completed
- Jan 12, 2024 (32 months after issuance)
- Review stops
- 5 stops across 2 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 15, 2021 | Mar 15, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 13, 2021 | Apr 13, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2021 | Apr 23, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2021 | May 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 17, 2021 | May 17, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Bruce Joseph Teel Bruce Teel Architect | Architect | C19940 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019