1375 24th Av
San Francisco permit 202103176763 · Sunset/Parkside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa#201811307126. alter site. the new includes interior renovations and horizontal expansion into the rear yard in the existing ground floor.
- Filed
- Mar 17, 2021
- Issued
- Nov 30, 2021 (8 months after filing)
- Completed
- Feb 22, 2024 (27 months after issuance)
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 2, 2021 | Apr 2, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 2, 2021 | Jun 1, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 2, 2021 | Sep 10, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 3, 2021 | Sep 27, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2021 | Oct 18, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Sep 27, 2021 | Oct 21, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2021 | Oct 18, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2021 | Oct 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2021 | Oct 21, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2021 | Oct 22, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 22, 2021 | Nov 30, 2021 | — |
Addendum 1: Arch, structural, title 24, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 7, 2021 | Dec 7, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 7, 2021 | Dec 23, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2021 | Feb 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2022 | Jan 27, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2022 | Jan 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 24, 2022 | Feb 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2022 | Mar 9, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Vanessa Liu | Architect | C37015 |
| Lisa Wai Sum Tse | Engineer | 4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025