763 University St
San Francisco permit 202103186830 · Portola
Cut down (e) side parapets to comply with planning complaint # 10564-enf. new flashing cap. comply with discretionary review (dr) action #2008.0147d
- Filed
- Nov 10, 2024
- Issued
- Mar 27, 2025 (5 months after filing)
- Completed
- Jan 27, 2026 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 3 times, by Planning, Building Inspection
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 18, 2021 | Mar 18, 2021 | — |
Building inspector Building Inspection · BID-INSP | Mar 23, 2021 | Mar 23, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 31, 2021 | May 13, 2021 | — |
Zoning review Planning · CP-ZOC | May 13, 2021 | Jun 13, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 14, 2021 | Oct 14, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Nov 7, 2022 | Jun 13, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2023 | Jun 21, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Nov 28, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2024 | Nov 6, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 4, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2024 | Nov 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 12, 2024 | Nov 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Dec 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2024 | Nov 14, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 12, 2024 | Mar 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2025 | Feb 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2025 | Jan 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 6, 2025 | Feb 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 14, 2025 | Mar 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Mark Elliott Bucciarelli Baukunst | Architect | C-23159 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022