CheckMyDesigner

200 Randolph St

San Francisco permit 202103237113 · Oceanview/Merced/Ingleside

Commercial or tenant improvement (type unconfirmed)Full plan reviewComplete
Street view · Sep 2014
Google Street View of 200 Randolph St, Sep 2014
Scope of work
As written on the permit application.

Priority 100% affordable housing. community rm bldg:1 of 3 structures. no dwelling units in this structure. proposed work is rehab. of comm. rm, addition of management & resident office. replacment of cement plaster cladding, n windows & roofing. site work includes all new flatwork & landscaping...

Timeline
Key dates from the city record.
Filed
Mar 23, 2021
Issued
Sep 14, 2021 (6 months after filing)
Completed
Aug 23, 2023 (23 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
50 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
12 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 23, 2021—

Permit Processing Center

Building Inspection · PPC

Aug 13, 2021—

Zoning review

Planning · CP-ZOC

Jul 13, 2021—

Building plan review

Building Inspection · BLDG

Aug 9, 2021—

Fire prevention review

Fire Department · SFFD

Jul 29, 2021—

Street use and mapping

Public Works · DPW-BSM

Apr 29, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 8, 2021—

Planning neighborhood notice

Planning · CP-NP

May 26, 2021—

Street use and mapping

Public Works · DPW-BSM

Jul 14, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 2, 2021—

Zoning review

Planning · CP-ZOC

Aug 2, 2021—

Street use and mapping

Public Works · DPW-BSM

Aug 2, 2021—

Zoning review

Planning · CP-ZOC

Aug 2, 2021—

Central Permit Bureau

Building Inspection · CPB

Sep 14, 2021—

Building Inspection

417-86

Sep 9, 2021—

Addendum 1: Structural

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2021—

Building plan review

Building Inspection · BLDG

Dec 17, 2021—

Fire prevention review

Fire Department · SFFD

Oct 21, 2021—

Street use and mapping

Public Works · DPW-BSM

Oct 20, 2021—

Permit Processing Center

Building Inspection · PPC

Dec 21, 2021—

Street use and mapping

Public Works · DPW-BSM

Dec 21, 2021—

Central Permit Bureau

Building Inspection · CPB

May 10, 2022—

Addendum 2: Architectural

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2021—

Building plan review

Building Inspection · BLDG

Oct 29, 2021—

Fire prevention review

Fire Department · SFFD

Oct 13, 2021—

Permit Processing Center

Building Inspection · PPC

Apr 28, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Feb 9, 2022—

Electrical plan review

Building Inspection · MECH-E

Oct 26, 2021—

Building plan review

Building Inspection · BLDG

Jan 4, 2022—

Electrical plan review

Building Inspection · MECH-E

Dec 28, 2021—

Fire prevention review

Fire Department · SFFD

Dec 27, 2021—

Disability access review

Mayor's Office on Disability · MOD

Apr 22, 2022—

Building plan review

Building Inspection · BLDG

Apr 27, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Apr 27, 2022—

Electrical plan review

Building Inspection · MECH-E

Apr 27, 2022—

Fire prevention review

Fire Department · SFFD

Apr 26, 2022—

Central Permit Bureau

Building Inspection · CPB

May 10, 2022—

Addendum 3: Mep | electrical

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2021—

Mechanical and energy plan review

Building Inspection · MECH

Feb 9, 2022—

Electrical plan review

Building Inspection · MECH-E

Dec 7, 2021—

Fire prevention review

Fire Department · SFFD

Feb 16, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 21, 2021—

Permit Processing Center

Building Inspection · PPC

Feb 17, 2022—

Electrical plan review

Building Inspection · MECH-E

Feb 17, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 16, 2022—

Central Permit Bureau

Building Inspection · CPB

May 10, 2022—

Addendum 4: Alarm

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 18, 2022—

Fire prevention review

Fire Department · SFFD

Jun 29, 2022—

Permit Processing Center

Building Inspection · PPC

Jul 8, 2022—

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$2,455,594
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Pamela Anne Collier

Levy Design Partners

ArchitectC14940
Christopher James WoodEngineerC72184
Steven Forrest Curry

Murphy Burr Curry

EngineerS3364
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202103237113 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record