2746 Filbert St
San Francisco permit 202103257298 · Marina
Renovations to existing single family dwelling including: -new horizontal addition at rear. -new rear yard patio & landscaping. -new stair penthouse to new roof deck. -new 2 story infill at rear. -new infill behind facade at exterior entry porch. -interior remodel on all 3 floors.
- Filed
- Mar 25, 2021
- Issued
- May 11, 2022 (14 months after filing)
- Completed
- Not completed yet
- Review stops
- 16 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 25, 2021 | Apr 5, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2021 | Oct 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Aug 25, 2021 | Oct 20, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 21, 2021 | Jan 6, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2022 | Feb 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 17, 2022 | Feb 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 23, 2022 | Apr 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2022 | Apr 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2022 | May 11, 2022 | — |
Addendum 1: Arch, struct, t24, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 24, 2022 | May 24, 2022 | — |
Building plan review Building Inspection · BLDG | May 24, 2022 | Jul 19, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2022 | Aug 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2022 | Sep 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2022 | Sep 7, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 13, 2022 | Sep 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2022 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $497,000
| Name | Role | License on permit |
|---|---|---|
| Eric Harry Hartz Gast Architects | Architect | C-33994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2017