801 Sanchez St
San Francisco permit 202103307534 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 201902284043-s3. enlarged basement and revised layout. revised layout on 1st and 2nd floors, relocate and add skylights. relocated pv panels on roof.
- Filed
- Mar 30, 2021
- Issued
- Jun 27, 2023 (27 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 30, 2021 | Mar 30, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 6, 2021 | Apr 6, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2021 | Apr 12, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2021 | Jul 27, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 12, 2021 | Jun 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2021 | Jan 18, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Sep 8, 2021 | Sep 10, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 10, 2021 | Sep 16, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2021 | Jun 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2021 | Oct 21, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Jan 13, 2023 | Jan 13, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 18, 2023 | May 24, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2023 | Feb 1, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 15, 2023 | Feb 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 15, 2023 | Mar 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2023 | Mar 10, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 13, 2023 | Mar 23, 2023 | — |
Zoning review Planning · CP-ZOC | May 25, 2023 | May 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2023 | May 30, 2023 | — |
Fire prevention review Fire Department · SFFD | May 30, 2023 | Jun 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 6, 2023 | Jun 6, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 20, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2023 | Jun 23, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 23, 2023 | Jun 23, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2023 | Jun 27, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Joshua W Aidlin Aidlin Darling Design | Architect | C28109 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2011