730 Stanyan St
San Francisco permit 202103317637 · Haight Ashbury
New 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot. the project will provide 160 100% affordable housing rental units.
- Filed
- Mar 31, 2021
- Issued
- Dec 28, 2022 (21 months after filing)
- Completed
- Nov 19, 2025 (35 months after issuance)
- Review stops
- 114 stops across 8 departments
- Comments issued
- 21 times, by Mayor's Office on Disability, Building Inspection, Fire Department, Permit Center
- Put on hold
- 20 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 31, 2021 | Mar 31, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2021 | Dec 28, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 1, 2021 | Jun 21, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2021 | Jul 13, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 12, 2021 | Jun 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2021 | Apr 12, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 12, 2021 | Oct 19, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2021 | Oct 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2022 | Feb 17, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Feb 24, 2022 | Jun 15, 2022 | — |
Urban forestry Public Works · DPW-BUF | Apr 5, 2022 | Aug 1, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2022 | Jul 19, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2022 | Jul 20, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2022 | Jul 27, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 19, 2022 | Jul 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2022 | Jul 20, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Jul 19, 2022 | Jul 20, 2022 | — |
Development fee collection Building Inspection · DFCU | Jul 28, 2022 | Jul 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2022 | Dec 28, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 2, 2022 | Sep 26, 2022 | — |
Public health review Public Health · HEALTH | Nov 28, 2022 | Dec 28, 2022 | — |
Addendum 1: Health - sfhc article 22b (no plans)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2023 | Jan 6, 2023 | — |
Public health review Public Health · HEALTH | Jan 6, 2023 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 6, 2023 | Jan 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2023 | Jun 15, 2023 | — |
Addendum 2: Grading, below grade utilities, ground improvement, underground mep, foundation, and super structure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 25, 2023 | Jan 25, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2023 | Apr 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 25, 2023 | Jan 26, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 25, 2023 | Feb 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2023 | Jun 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 25, 2023 | Jun 15, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jan 26, 2023 | Jan 26, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 3, 2023 | Mar 13, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 11, 2023 | May 26, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 5, 2023 | Jun 5, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 14, 2023 | Jun 14, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 14, 2023 | Jun 15, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 15, 2023 | Jun 15, 2023 | — |
Addendum 3: Architecture + mechanical, electrical, plumbing, photovoltaic, exterior building management
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Disability access review Mayor's Office on Disability · MOD | Jan 20, 2013 | Oct 13, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2023 | Jan 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 12, 2023 | Jan 30, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 12, 2023 | Sep 21, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2023 | Sep 27, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 12, 2023 | Jan 25, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2023 | Jan 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 12, 2023 | Jan 31, 2024 | — |
Electrical plan review Building Inspection · MECH-E | Jan 17, 2023 | Sep 18, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Jan 20, 2023 | Sep 18, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2023 | Jun 14, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 3, 2023 | Jan 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Sep 20, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 18, 2023 | Sep 18, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 15, 2023 | Nov 27, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 15, 2023 | Nov 15, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 15, 2023 | Nov 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2023 | Nov 17, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2023 | Nov 21, 2023 | Issued Comments |
Disability access review Mayor's Office on Disability · MOD | Dec 1, 2023 | Dec 5, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 14, 2023 | Dec 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2023 | Dec 18, 2023 | Approved |
Disability access review Mayor's Office on Disability · MOD | Jan 10, 2024 | Jan 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 12, 2024 | Jan 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 12, 2024 | Jan 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2024 | Jan 18, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 12, 2024 | Jan 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2024 | Jan 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2024 | Feb 2, 2024 | Administrative |
Addendum 4: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2023 | May 26, 2023 | — |
Building plan review Building Inspection · BLDG | May 26, 2023 | Sep 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 26, 2023 | Sep 20, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 26, 2023 | Sep 20, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 14, 2023 | Sep 20, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Sep 20, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2023 | Sep 21, 2023 | Administrative |
Addendum 5: Building envelope/unitized glass fiber reinforced concrete panel
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 1, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 1, 2023 | May 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Jan 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2023 | Dec 18, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 4, 2023 | Jan 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 15, 2024 | Feb 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Apr 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2024 | May 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 6, 2024 | May 7, 2024 | Administrative |
Addendum 6: Steel stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Nov 29, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Dec 12, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Dec 6, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 29, 2023 | Jan 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 2, 2024 | Jan 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 3, 2024 | Jan 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2024 | Jan 10, 2024 | Administrative |
Addendum 7: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2024 | Mar 8, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 8, 2024 | Mar 8, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 19, 2024 | Mar 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 21, 2024 | Mar 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2024 | Mar 25, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 25, 2024 | Mar 30, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 25, 2024 | Jun 25, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 6, 2024 | Jun 11, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2024 | Jun 26, 2024 | Administrative |
Addendum 8: Fire alarm and 2-way communication/emergency responder radio communications systems
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2024 | Aug 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2024 | Aug 7, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Aug 3, 2024 | Aug 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2024 | Aug 19, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 7, 2024 | Jan 8, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 24, 2024 | Oct 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 7, 2025 | Jan 7, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2025 | Jan 21, 2025 | Administrative |
Addendum 9: Storm water control plumbing review
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 15, 2023 | Sep 15, 2023 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Sep 15, 2023 | Sep 26, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 15, 2023 | Sep 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2023 | Sep 27, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $108,000,000
| Name | Role | License on permit |
|---|---|---|
| Yakuh Django Askew Y.A. Studio | Architect | C29776 |
| Jason J. Ling Urban Design Consulting Eng | Engineer | C60493 |
| David Clifton Mar Tipping-Mar Structural Eng | Engineer | S3951 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026