1120 A Shotwell St
San Francisco permit 202104088185 · Mission
To erect 3 stories, no basement, type v-a, 3 units residential building. sprinklers per nfpa 13 and sprinkler monitoring per nfpa 72 under separate permits.
- Filed
- Apr 8, 2021
- Issued
- May 11, 2022 (13 months after filing)
- Completed
- Dec 6, 2024 (31 months after issuance)
- Review stops
- 36 stops across 5 departments
- Comments issued
- None
- Put on hold
- 14 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 16, 2021 | Apr 16, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 19, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2021 | Dec 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 2, 2021 | Mar 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2022 | Apr 6, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2022 | Mar 18, 2022 | — |
Urban forestry Public Works · DPW-BUF | Apr 6, 2022 | Apr 26, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 29, 2022 | May 3, 2022 | — |
Development fee collection Building Inspection · DFCU | May 2, 2022 | May 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 3, 2022 | May 11, 2022 | — |
Addendum 1: Foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 16, 2022 | May 16, 2022 | — |
Building plan review Building Inspection · BLDG | May 16, 2022 | Jul 29, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 29, 2022 | Aug 12, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2022 | Aug 26, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 25, 2022 | Aug 25, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2022 | Aug 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 29, 2022 | Aug 31, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2022 | Sep 2, 2022 | — |
Addendum 2: Architectural & mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 26, 2022 | Oct 26, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 27, 2022 | Dec 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2022 | Mar 29, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Dec 8, 2022 | Jan 9, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 18, 2023 | Jul 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2023 | Aug 7, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 29, 2023 | Apr 5, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 5, 2023 | Apr 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2023 | Apr 13, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 13, 2023 | May 11, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2023 | Jul 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2023 | Jul 11, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 11, 2023 | Sep 25, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2023 | Jul 18, 2023 | — |
Zoning review Planning · CP-ZOC | Sep 25, 2023 | Oct 4, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 4, 2023 | Oct 13, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 13, 2023 | Oct 17, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Oct 18, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects Llp | Architect | C24585 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019