235 28th St
San Francisco permit 202104148501 · Noe Valley
3rd floor addition to existing single residence in order to provide 3 bedrooms and 2 bathrooms on top floor. remodel of existing first floor bedrooms to create family room, exercise area, and home office.
- Filed
- Apr 14, 2021
- Issued
- Jun 26, 2023 (26 months after filing)
- Completed
- Oct 23, 2025 (28 months after issuance)
- Review stops
- 25 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2021 | Apr 19, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 28, 2021 | Feb 1, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Oct 18, 2022 | Feb 1, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 23, 2023 | Jan 23, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 2, 2023 | May 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2023 | Apr 28, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2023 | May 26, 2023 | — |
Fire prevention review Fire Department · SFFD | May 31, 2023 | May 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2023 | Jun 2, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 5, 2023 | Jun 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 6, 2023 | Jun 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 8, 2023 | Jun 26, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 5, 2023 | Sep 15, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Oct 20, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2023 | Oct 31, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Dec 14, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 26, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 15, 2023 | Jan 25, 2024 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Dec 4, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Jan 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2024 | Jan 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 12, 2024 | Jan 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2024 | Jan 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2024 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Anne Clark Forell Anne Forell Architecture | Architect | C27146 |
| Shaun Edward Moynahan Semco Engineering Inc. | Engineer | S-4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015