376 Hill St
San Francisco permit 202104208908 · Noe Valley
To erect 3 stories, 1 basement, type v-b over i-b, single family residence w/ an adu at basement level. (adu scope of work under separate permit)
- Filed
- Apr 20, 2021
- Issued
- Jan 26, 2023 (21 months after filing)
- Completed
- Not completed yet
- Review stops
- 46 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 8 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 27, 2021 | Apr 27, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 28, 2021 | Jan 19, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2022 | Jan 13, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2022 | Sep 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 12, 2022 | Sep 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2022 | Dec 12, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 13, 2022 | Dec 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 15, 2022 | Dec 15, 2022 | — |
Development fee collection Building Inspection · DFCU | Dec 15, 2022 | Dec 15, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 15, 2022 | Jan 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | — | Oct 12, 2022 | — |
Addendum 1: Arch,mech,t-24 final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 6, 2023 | Feb 6, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 8, 2023 | Sep 14, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2023 | Jun 26, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 8, 2023 | Feb 23, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 8, 2023 | May 8, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 8, 2023 | Feb 8, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 8, 2023 | Feb 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 8, 2023 | May 27, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2023 | Jan 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 11, 2024 | Jan 25, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 29, 2024 | Feb 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 29, 2024 | Feb 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2024 | Apr 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 12, 2024 | Apr 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2024 | May 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 13, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 13, 2024 | Feb 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Jul 25, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Sep 24, 2024 | Sep 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 4, 2025 | Feb 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2025 | Feb 13, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2025 | Feb 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2025 | Feb 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2025 | May 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2025 | May 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2025 | May 19, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 13, 2025 | May 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2025 | May 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 13, 2025 | May 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 27, 2025 | Jun 3, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,700,000
| Name | Role | License on permit |
|---|---|---|
| Leonardo Emilio Marmol Marmol Radziner | Architect | C-22376 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025