125 Pope St
San Francisco permit 202105130336 · Excelsior
(n) 3 story addition to rear of (e) 3 story residence. remodel (e) spaces to remain, new stair, new kitchen, & new laundry rooms. house will change from (e) 2 bedroom, 1 office, 2 bathroom to proposed 4 bedroom, 1 office, 4 bathroom.
- Filed
- May 13, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 28, 2021 | Jun 28, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 28, 2021 | Jan 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Dec 13, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 13, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | Jan 14, 2025 | Feb 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2025 | Jan 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2025 | Jan 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Edward Stephan Kaplan Kaplan Architects | Architect | C12668 |
| Ernest Hartley Selander Selander Architects | Architect | C12715 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025