188 The Embarcadero
San Francisco permit 202105210786 · Financial District/South Beach
Voluntary seismic upgrade to an existing 8-story concrete office building w/a basement parking garage. structural improvements include installing concrete shear walls,collectors[i.e. steel, concrete, and fiberglass reinforced polymer (frp)] & fiberglass reinforced polymer(frp)column
- Filed
- May 21, 2021
- Issued
- Dec 1, 2021 (6 months after filing)
- Completed
- May 24, 2023 (18 months after issuance)
- Review stops
- 14 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 24, 2021 | May 26, 2021 | — |
Building plan review Building Inspection · BLDG | May 26, 2021 | Nov 12, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 5, 2021 | Nov 19, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 8, 2021 | Nov 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2021 | Oct 14, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 19, 2021 | Oct 19, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 19, 2021 | Oct 27, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 19, 2021 | Oct 27, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 27, 2021 | Nov 16, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2021 | Nov 22, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 23, 2021 | Nov 24, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 23, 2021 | Nov 24, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 24, 2021 | Nov 24, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 24, 2021 | Dec 1, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $4,800,000
| Name | Role | License on permit |
|---|---|---|
| Byron Kendrick Wong Des Architect & Engineering | Architect | C33768 |
| Robert George Pekelnicky Degenkolb Engineers | Engineer | S5083 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026