2335 Golden Gate Av
San Francisco permit 202105210845 · Lone Mountain/USF
Construct (n) approx 15,600 sf addition, 45-ft basketball practice facility on the usf lower campus. 1 full basketball court, 2 partial shooting/drills courts, coaches' offices, conf rms, restrms, & storage room.
- Filed
- May 21, 2021
- Issued
- Oct 4, 2022 (16 months after filing)
- Completed
- Nov 7, 2025 (37 months after issuance)
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 9 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2021 | May 26, 2021 | — |
Zoning review Planning · CP-ZOC | May 26, 2021 | Jul 28, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 29, 2021 | Jun 28, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 29, 2021 | Jun 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 5, 2021 | Aug 6, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 21, 2021 | Oct 21, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 15, 2022 | Jul 13, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 4, 2022 | Aug 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 16, 2022 | Jul 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2022 | Jun 1, 2022 | — |
Urban forestry Public Works · DPW-BUF | Mar 25, 2022 | Mar 25, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2022 | Jul 29, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 8, 2022 | Aug 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 16, 2022 | Sep 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2022 | Sep 22, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 22, 2022 | Sep 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 29, 2022 | Sep 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2022 | Oct 4, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Robert S Connelly Oculus | Architect | C27077 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015