1 Avenue Of The Palms
San Francisco permit 202105251034 · Treasure Island
Priority processing per mayor ed #17-02 to erect 5 stories 1 basement, type v-a over 1-a w/ 3hr podium 117 residential units, 3 retail shell spaces on ground floor, garage with 59 stalls and storage in the basement. treasure island parcel b1
- Filed
- May 25, 2021
- Issued
- Dec 10, 2021 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 34 stops across 6 departments
- Comments issued
- None
- Put on hold
- 8 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 25, 2021 | Jun 11, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 11, 2021 | Jun 17, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 11, 2021 | Oct 29, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 18, 2021 | Oct 8, 2021 | — |
Fire Department housing review Fire Department · SFFD-HQ | Jun 18, 2021 | Oct 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2021 | Aug 25, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2021 | Oct 7, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2021 | Oct 18, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 12, 2021 | Oct 25, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 12, 2021 | Oct 26, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 29, 2021 | Dec 10, 2021 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 17, 2021 | Jan 27, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2022 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2022 | Feb 8, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2022 | In progress | — |
Public health review Public Health · HEALTH | May 6, 2022 | Jul 31, 2023 | Administrative |
Public Health HEALTH-HP | Jul 31, 2023 | Jul 31, 2023 | Administrative |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2021 | Jan 27, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2022 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2022 | Feb 8, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2022 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Arch mep civil landscape
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 17, 2021 | Jan 27, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2022 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2022 | In progress | — |
Fire prevention review Fire Department · SFFD | Jan 27, 2022 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2022 | Feb 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2022 | Feb 23, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2022 | In progress | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2022 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Feb 17, 2022 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $55,000,000
| Name | Role | License on permit |
|---|---|---|
| Neil Bernard Kaye Natoma Architects Inc. | Architect | C32794 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2025