401 25th St
San Francisco permit 202105261127 · Bayview Hunters Point
To erect a 1 story type v building for sfmta bus wash
- Filed
- May 26, 2021
- Issued
- Oct 20, 2021 (5 months after filing)
- Completed
- Not completed yet
- Review stops
- 39 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 9 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2021 | Jun 16, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 16, 2021 | Jul 29, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 16, 2021 | Sep 16, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 22, 2021 | Sep 3, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 28, 2021 | Sep 15, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2021 | Jul 30, 2021 | — |
Public Works disability access review Public Works · PW-DAC | Jul 28, 2021 | Aug 11, 2021 | — |
Public health review Public Health · HEALTH | Jul 28, 2021 | Sep 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2021 | Sep 8, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 2, 2021 | Sep 2, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2021 | Sep 2, 2021 | — |
Public Works disability access review Public Works · PW-DAC | Sep 2, 2021 | Sep 9, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2021 | Oct 20, 2021 | — |
Development fee collection Building Inspection · DFCU | Sep 20, 2021 | Sep 20, 2021 | — |
Addendum 1: Exacavation, grading, building foundations,underground infrastructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 15, 2021 | Nov 22, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 22, 2021 | Aug 4, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 3, 2021 | Jun 6, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2021 | Jul 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2022 | Aug 24, 2022 | — |
Addendum 2: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 1, 2022 | Jul 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 1, 2022 | Aug 4, 2022 | — |
Public health review Public Health · HEALTH | Jul 5, 2022 | Jul 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2022 | Aug 24, 2022 | — |
Addendum 3: Arch,hvac,plumbing,stormwater,equipment,electrical & communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 19, 2022 | Apr 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2022 | In progress | — |
Building plan review Building Inspection · BLDG | Apr 20, 2022 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 20, 2022 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Apr 20, 2022 | In progress | — |
Fire Department SFFD-PRT | Apr 20, 2022 | Oct 21, 2022 | — |
Public Works disability access review Public Works · PW-DAC | Apr 20, 2022 | Oct 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2022 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2022 | Apr 29, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 20, 2022 | May 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 4: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 19, 2022 | Apr 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2022 | In progress | — |
Building plan review Building Inspection · BLDG | Apr 20, 2022 | Dec 2, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2022 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $9,300,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Joseph Maloney Sfmta | Architect | C16935 |
| Benny Ng | Engineer | C72192 |
| Daniel Li | Engineer | C84755 |
| Raymond Lui Sfdpw | Engineer | S4094 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026