94 Denslowe Dr
San Francisco permit 202105281234 · West of Twin Peaks
1-story rear yard addition. included in the addition is an exercise rm, bedrm, laundry rm and 2 full baths. remodel of (e) kitchen & baths. enclose from porch and relocate front door. site plans.
- Filed
- May 28, 2021
- Issued
- Aug 18, 2022 (15 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 29, 2021 | Jun 29, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 29, 2021 | Jan 18, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Nov 16, 2021 | Nov 30, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2022 | Jan 13, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 19, 2022 | Feb 22, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 19, 2022 | May 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2022 | Apr 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2022 | Apr 26, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 23, 2022 | May 24, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jul 12, 2022 | Jul 12, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 15, 2022 | Jul 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 21, 2022 | Aug 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2022 | Aug 18, 2022 | — |
Addendum 1: Foundation,t-24, architecture, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2022 | Aug 29, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 30, 2022 | May 1, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 13, 2022 | May 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2022 | May 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 16, 2022 | Nov 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2022 | Apr 27, 2023 | — |
Building plan review Building Inspection · BLDG | May 1, 2023 | May 1, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | May 1, 2023 | May 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2023 | May 1, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 2, 2023 | May 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2023 | May 26, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $203,400
| Name | Role | License on permit |
|---|---|---|
| Andrew Bruce Morrall Andrew Morrall Architect | Architect | C26696 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022