Priority: renovate (e) 1st floor unit and convert portion of (e) laundry and storage space into (n) habitable space.
- Filed
- Jun 2, 2021
- Issued
- Jun 1, 2022 (12 months after filing)
- Completed
- Jan 30, 2023 (8 months after issuance)
- Review stops
- 23 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 2, 2021 | Jun 22, 2021 | — |
Apartment and hotel inspection Building Inspection · HIS | Jun 2, 2021 | Jun 2, 2021 | — |
Code enforcement Building Inspection · CES | Jun 10, 2021 | Jun 10, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 22, 2021 | Jul 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 22, 2021 | May 17, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 26, 2021 | Feb 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2021 | Mar 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 26, 2021 | Feb 17, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2021 | Mar 10, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2022 | Feb 17, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 9, 2022 | Mar 16, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2022 | Mar 10, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 9, 2022 | Mar 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2022 | Mar 18, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 25, 2022 | Apr 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 25, 2022 | Apr 19, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2022 | May 9, 2022 | — |
Zoning review Planning · CP-ZOC | May 10, 2022 | May 10, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 10, 2022 | May 11, 2022 | — |
Fire prevention review Fire Department · SFFD | May 10, 2022 | May 12, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 10, 2022 | May 12, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 16, 2022 | Jun 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2022 | May 17, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Jaime Neilson Jaime Neilson, P.E., S.E | Engineer | 5125 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025