1501 Sunnydale Av
San Francisco permit 202106031523 · Visitacion Valley
Sunnydale block 3a (lot 3)-priority 100% housing project. to erect 5-story, 4 stories of type 5 over 1 story of type 1, mixed use bldg with child center, retail, restaurants, wellness center and 80 residential units.
- Filed
- Jun 3, 2021
- Issued
- Aug 10, 2022 (14 months after filing)
- Completed
- Apr 28, 2025 (33 months after issuance)
- Review stops
- 123 stops across 8 departments
- Comments issued
- 18 times, by Fire Department, Building Inspection, Permit Center
- Put on hold
- 11 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 3, 2021 | Jun 11, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 11, 2021 | Feb 25, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 11, 2021 | Aug 1, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Jul 27, 2021 | Apr 28, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 27, 2021 | Apr 20, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 27, 2021 | Mar 2, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2021 | Sep 29, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 27, 2021 | Oct 19, 2021 | — |
Public health review Public Health · HEALTH | Jul 27, 2021 | Dec 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2022 | Jul 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2022 | Jan 13, 2022 | — |
Public health review Public Health · HEALTH | Jan 7, 2022 | Jan 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2022 | Mar 4, 2022 | — |
Public health review Public Health · HEALTH | Feb 25, 2022 | Mar 2, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2022 | Jul 26, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Jul 25, 2022 | Aug 1, 2022 | — |
Development fee collection Building Inspection · DFCU | Jul 25, 2022 | Jul 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2022 | Aug 10, 2022 | — |
Addendum 1: Civil and grading
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 2, 2022 | Sep 2, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 2, 2022 | Sep 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2022 | Sep 26, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 2, 2022 | Oct 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2022 | Jun 15, 2023 | — |
Addendum 2: Structural (foundation and superstructure)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 2, 2022 | Sep 2, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 2, 2022 | Oct 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 2, 2022 | Dec 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2022 | Dec 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2022 | Jun 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | — | Sep 26, 2022 | — |
Addendum 3: Architectural, landscape, mechanical, electrical, plumbing, and mod
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 6, 2022 | Sep 6, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 6, 2022 | Mar 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 6, 2022 | Feb 7, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 6, 2022 | Mar 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2022 | Sep 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2022 | Sep 26, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Sep 6, 2022 | Mar 28, 2023 | — |
Zoning review Planning · CP-ZOC | Sep 6, 2022 | Mar 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 6, 2022 | Apr 24, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Nov 10, 2022 | Mar 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 21, 2023 | Mar 27, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Mar 23, 2023 | Mar 24, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 12, 2023 | Apr 21, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2023 | Apr 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 12, 2023 | Apr 14, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2023 | Jun 23, 2023 | — |
Addendum 4: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 21, 2023 | Jul 21, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 21, 2023 | Aug 15, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 21, 2023 | Jan 31, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 15, 2023 | Nov 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 26, 2023 | Dec 26, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 30, 2024 | Jan 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2024 | Feb 13, 2024 | Administrative |
Addendum 5: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 2, 2023 | Oct 2, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 2, 2023 | Nov 2, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 2, 2023 | Sep 16, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 7, 2024 | Mar 8, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 29, 2024 | Apr 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 6, 2024 | Jun 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Aug 26, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2024 | Sep 26, 2024 | Administrative |
Addendum 6: Emergency responder radio coverage system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Jan 9, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 20, 2023 | Nov 20, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 28, 2023 | Jan 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2024 | Jan 16, 2024 | Administrative |
Addendum 7: Exterior building maintenance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 26, 2023 | Sep 26, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Oct 12, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 26, 2023 | Oct 10, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 26, 2023 | Mar 11, 2024 | — |
Building plan review Building Inspection · BLDG | Jan 17, 2024 | Feb 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 17, 2024 | Jan 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Feb 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 21, 2024 | Feb 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2024 | Mar 19, 2024 | Administrative |
Addendum 8: Photovoltaic array
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 26, 2023 | Sep 26, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Oct 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2023 | Oct 17, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 26, 2023 | Oct 12, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 26, 2023 | Mar 14, 2024 | — |
Electrical plan review Building Inspection · MECH-E | Oct 2, 2023 | Oct 3, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Dec 14, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 29, 2023 | Dec 5, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Nov 30, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 29, 2023 | Nov 30, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 2, 2024 | Feb 2, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 7, 2024 | Feb 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 7, 2024 | Feb 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Feb 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Feb 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 14, 2024 | Mar 18, 2024 | Administrative |
Addendum 9: Stormwater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2023 | Dec 21, 2023 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Dec 21, 2023 | Jan 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 21, 2023 | Jan 25, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2024 | Jan 26, 2024 | Administrative |
Addendum 10: Elevators
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 19, 2024 | Jan 24, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 23, 2024 | Jan 23, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jan 29, 2024 | Jan 29, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 29, 2024 | Feb 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2024 | Feb 5, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 5, 2024 | Mar 29, 2024 | — |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Feb 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2024 | Feb 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2024 | Mar 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2024 | Mar 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2024 | Mar 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Mar 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 29, 2024 | Apr 1, 2024 | Administrative |
Addendum 11: Evacuation signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 16, 2024 | Apr 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2024 | Apr 23, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 21, 2024 | Apr 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 23, 2024 | May 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 23, 2024 | May 3, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 3, 2024 | May 7, 2024 | Administrative |
Addendum 12: Steel-framed stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 31, 2024 | Jun 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2024 | Jun 10, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Jun 7, 2024 | Jun 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 10, 2024 | Jun 10, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 10, 2024 | Jun 25, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 10, 2024 | Jun 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 10, 2024 | Jun 26, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2024 | Jun 27, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $53,000,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Elias Simons David Baker Architects | Architect | C30025 |
| Ryan Jay Beaton Kpff | Engineer | 82786 |
| David Clifton Mar Tipping-Mar Structural Eng | Engineer | S3951 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025